Manta Bay Construction Update Q4, 2025
Phase 1 – Enabling Works (100% Completed)
- Soil investigation and topographical survey completed
- Site mobilization works completed
- Enabling works completed
- Dewatering works completed
- Piling works completed
Phase 2 – Main Work Stream (In Progress)
- Foundation works are 50% completed
- Substructure waterproofing works are 90% completed
Phase 3 – Services & Systems (Initiated)
- MEP works commenced and currently at 1% progress