Manta Bay Construction Update Q4, 2025

Phase 1 – Enabling Works (100% Completed)

  • Soil investigation and topographical survey completed
  • Site mobilization works completed
  • Enabling works completed
  • Dewatering works completed
  • Piling works completed

Phase 2 – Main Work Stream (In Progress)

  • Foundation works are 50% completed
  • Substructure waterproofing works are 90% completed

Phase 3 – Services & Systems (Initiated)

  • MEP works commenced and currently at 1% progress