Manta Bay Construction Update Q3, 2025

Phase 1 – Enabling Works (100% Completed)

  • Piling completed
  • Shoring system completed
  • Soil improvement completed
  • Dewatering completed

Phase 2 – Main Work Stream (In Progress)

  • Mobilisation and site offices completed
  • Site levelling, compaction, and anti-termite treatment are ongoing
  • Casting of Plain Cement Concrete (PCC) is ongoing
  • Blockwork for dead shuttering and boundary wall is ongoing
  • Reinforcement for the tower crane foundation is ongoing

Site housekeeping and safety preparations are ongoing